Due to the completion of pavement repairs and the installation of retractable bollards to prevent vehicles from entering the city center, tram service on Masarykova Street will not be possible from the start of service on Monday, May 18, 2026, until the work is completed (expected by the end of June 2026), which will require comprehensive changes to tram routes in the city center.
Tram Line 4 will operate only on the section between Náměstí Míru and Náměstí Svobody.
Tram line 9 will run in both directions between Česká and Hlavní nádraží via Šilingrovo náměstí and Nové sady.
• It will not serve the Náměstí Svobody and Zelný trh stops.
• It will serve the Česká stop on Joštova Street (platforms 1 and 2).
• At the Hlavní nádraží hub, it will serve platforms 3 and 4 together with lines 8 and 10.
Tram line 10 will run in both directions between Česká and Hlavní nádraží via Šilingrovo náměstí and Nové sady.
• It will not serve the Malinovského náměstí stop.
• It will serve the Česká stop on Česká Street (platforms 3 and 4).
• At the Main Station hub, it will serve platforms 3 and 4 together with lines 8 and 9.
Tram Line 12 will run in both directions between Česká and Hlavní nádraží via Malinovského náměstí.
• It will not serve the Šilingrovo náměstí and Nové sady stops.
• It will continue to serve the Česká stop on České Street (platforms 3 and 4).
• At the Hlavní nádraží hub, it will serve platforms 5 and 6 (near the trolleybus loop).
Replacement service for Line 4 will be provided by temporary tram Line 14 on the route Náměstí Míru – (following the route of Line 4) – Komenského náměstí – Šilingrovo náměstí – Nové sady – Main Station (platforms 1 and 2) – Malinovského náměstí – (following the original route and stops of Line 4) – Obřany, Babická.
• Selected services on weekdays from 7 a.m. to 6 p.m. will operate only on the section Malinovského náměstí – Obřany, Babická.